Report on the Condition of the Fabric
When I undertook my Quinquennial Inspection
in 1998, it became apparent that the overall condition
of the fabric of Ripon Cathedral was good. To a
large degree this has been the result of the continuing
efforts by the Dean & Chapter over the past
fifteen years to undertake the necessary repair
work as required. Nonetheless, my Inspection showed
that there are still areas of concern, most notably
to the roofs of the Cathedral as well as the stonework
to the North Transept.
In conjunction with English Heritage, a five
year programme of necessary major repairs was prepared.
The first area of concern was the condition of the
roofs to the two West Towers. The reroofing of the
Southwest Tower has been completed. That to the Northwest
Tower is now in hand and will be completed by July.2002.
Once this work has been completed, the next task
facing the Cathedral is the reroofing of the Nave.
This pitched roof, some 40 metres long, is covered
in Welsh slates laid to diminishing courses. It dates
from the 1870s when Gilbert Scott undertook his major
restoration of the Cathedral. As the slates are,
therefore, some 130 years old they have come to the
end of their natural life. The Dean & Chapter
are faced with an ongoing problem of slipping, cracked
or broken slates to the Nave roof. Over the past
eighteen months, when the weather has been particularly
poor, the situation has reached a critical stage.
If reroofing is not undertaken within the next two
years, major problems may well arise within the interior
of the Cathedral. At present, estimates are being
sought for the cost of reslating the Nave but it
is anticipated that these are likely to be in the
region of some £300,000. The Chapter hopes to make
an application to English Heritage to part fund this
work. In addition to the slates, the parapet gutters,
which at some stage were covered in asphalt, will
also need to be renewed, preferably in leadwork.
Following on from the repairs to the Nave,
the releading of the central Tower roof will then
follow. After these reroofing works are undertaken,
we will then need to return to repairing the stonework
as previously stated, to the North Transept and North
elevation of the Choir.
Although these are the major areas of concern,
there are ongoing needs for other repairs to be undertaken
which arise from time to time. Examples of these
have been resetting loose and dangerous floor slabs
within the Cathedral, the relaying of defective drains
to the Southeast and the complete renewal of the
tiled central Aisle to the Choir.